Gokuldham Haveli Construction Phase 1
Goal
Finish the first phase of construction by Begining of April.
We are working towards the goal very well. Here are the milestones achieved so far:
1. Land Acquisition (Acquired and Paid)2. Bhoomi Poojan (Done)
3. Land Disturbance Permit (Received)
4. Site Work (Completed with some Vaishnav loan)
5. Steel Building (Received and on site)
6. Construction Permit (Received - 9/8/2016)
7. Construction Foundation (Completed)
8. Steel structure erection (Completed)
9. Outside Framing and Covering (Completed)
10. Internal Framing (Completed)
11. Outside Stuco (Completed)
12. Plumbing (In progress)
13. Electricals (In progress)
14. Marbel and Tiles (In progress)
15. Low power wiring (In progress)